The 5371 Boundary Road Pipeline Project is a customer-driven project for a new natural gas pipeline to be located primarily along Boundary Road in Navan, on the municipal boundary between the City of Ottawa and Township of Russell.
The project will require the installation of a 0.7 km, 4-inch steel pipeline and a 9.4 km, 4-inch-polyethylene pipeline and a new district station. District stations are pressure regulating stations that reduce natural gas pressure and feed lower pressure networks safely.
The project is subject to Ontario Energy Board (OEB) approval and if approved, construction may begin early in 2024 and be completed by the end of 2024.
Project status/timeline
-
Feasibility
-
Environmental studies
-
Regulatory review
-
Regulatory approval
-
Under Construction
-
In-service
Project status/timeline
-
Feasibility
-
Environmental studies
-
Regulatory review
-
Regulatory approval
-
Under Construction
-
In-service