This project will replace aging natural gas pipelines in downtown Salt Lake City.
Project updates
June 14, 2024
200 South; 400 West to 200 West:
Through September 2024, our contractor will continue replacing the aging gas line along 200 south between approximately 250 West and 400 West.
Over the next couple of weeks, they will finish replacing the pipe between 300 West and 400 West and get the trench in the middle of the road backfilled, then continue replacing the plastic pipe on the north side of the road heading west.
- All westbound lanes are CLOSED during the day between 200 West and 300 West.
- At least one eastbound travel lane will be maintained at all times on 200 South within our project area.
- There may be limited on-street parking available during construction activities, especially on the north side of 200 South.
- Business, parking garage, and sidewalk access will be maintained.
Work will typically take place between the hours of 7 a.m. and 7 p.m., Monday through Friday. Weekend and night work may take place on occasion if needed.
- Pedestrian routes and crossings will remain unobstructed during this work.
- Business and parking garage access will be maintained.
- Nearby residents and businesses can expect increased noise, dust, and vibration associated with construction.
Construction schedules are always subject to change due to weather or other unforeseen circumstances.
Project information
Project overview
Need for the project: These improvements are necessary for Enbridge Gas Utah to keep pace with growing customer demand for natural gas, maintain overall system integrity and continue providing safe and reliable service.
Location: This section of natural gas pipeline is located in downtown Salt Lake City. Work will take place at all intersections of 200 South from 400 West to 200 South. To minimize the inconvenience to businesses and residences, Enbridge Gas is working in conjunction with Salt Lake City's 200 South corridor project.
Construction schedule: We are committed to completing this work as quickly and with as little inconvenience to local businesses and residents as possible. Crews are scheduled to start in Spring 2023. To expedite construction, multiple crews may be working simultaneously at various locations and may perform nighttime and weekend work. No interruption to residents' natural gas service is anticipated during this project. Work will be completed in two phases. Phase I will start in Spring 2022 and end in Winter 2022. Phase II will start in Spring 2023 and will continue into 2024.
To provide room for crews and equipment, some temporary lane restrictions, especially at intersections, will be necessary. Please drive carefully and obey all signs and flaggers. To avoid congestion in construction zones, motorists are advised to use alternate routes when possible and to allow plenty of travel time to get where they're going. At all times, our crews will make every effort to maintain access to businesses and driveways in construction zones.
We appreciate your patience.
Construction process
Enbridge Gas Utah is committed to completing this project safely and on schedule while minimizing as much as possible any inconvenience to local businesses and residents. To accomplish this, some work may be performed at night and on weekends. This will reduce impacts on morning and evening commutes. We will adhere to all county noise-reduction ordinances.
Construction zones
For pipe buried beneath streets or highways, construction may require intermittent closures of one or more lanes of traffic. Driveways also may be occasionally blocked by excavation work, otherwise they will be plated to maintain access during business hours and at night and on weekends.
Before construction starts in front of any home or business, a representative will contact the owner or resident to discuss options for maintaining driveway access. Signs notifying the public that businesses remain open during construction are available.
To finish construction on schedule and as quickly as possible, the project is divided into sections, or "spreads." This allows multiple crews to work simultaneously at different locations. Work zones can range from a single intersection to several blocks long. At any one location the amount of time to cut pavement, install new pipe and replace asphalt can range from several days to several weeks.
The public can do its part to ensure construction proceeds safely and on time by finding alternative routes, driving carefully in construction zones and keeping children away from construction sites.
Enbridge Gas works closely with city and state transportation officials to ensure safety and minimize inconvenience to drivers and pedestrians. However, for public safety it may be necessary to temporarily close streets and sidewalks or restrict vehicle and pedestrian traffic. As mentioned, driveways may occasionally be blocked by excavation work. We will make every effort to keep these inconveniences as brief as possible. Your patience is appreciated.
If you have questions or concerns, do not hesitate to contact us.
Steps during construction
Following are brief descriptions of the steps involved in pipeline removal and construction:
- Locate buried utilities - The area below city streets can be a maze of underground utilities. To avoid damaging these facilities, a procedure known as potholing is used prior to trenching to identify the exact vertical and horizontal location of existing infrastructure, including the pipeline to be replaced.
- Move existing utilities - Before trenching (see next step), all water and natural gas service lines that cross the existing pipe will be moved to a lower depth. This will minimize the risk of interrupting water- or gas-service to individual homes or businesses once actual construction begins.
- Dig trench - After the pipe has been located and purged of gas and service lines in the trench zone moved, the pavement above the existing pipe is cut and removed. Then equipment is brought in to dig the trench. The depth of the natural gas pipeline trench will be determined by the location of the existing pipe and other utilities. As the trench is dug, the soil is loaded into trucks and hauled away for disposal in a designated landfill.
- Remove old pipe - Sections of pipe to be removed are cut into lengths, lifted from the trench, loaded onto trucks and hauled away for proper disposal.
- Deliver and "string" new pipe - New pipe is manufactured and inspected to ensure it meets industry and federal safety standards. Pipe sections are then delivered by truck to the construction site where they are placed end-to-end (or "strung") on skids adjacent to the trench. If necessary, a hydraulic machine bends pipe sections to fit around obstacles or conform to the direction of the trench.
- Weld new pipe together and coat - Welding crews join the sections of pipe together into a continuous length. Each welded joint is visually inspected, x-rayed and then coated for protection.
- Lower pipe into trench - Using one or more tractors, crews lift and then carefully lower the welded sections of pipe into the trench. Final welds are made to "tie-in" any unconnected sections.
- Backfill trench - Under streets, in place of the removed soil, a mixture known as "flowable fill" is used to backfill the trench. In other areas, the original soil is replaced.
- Pressure test new pipe - After it's buried and before it's put into service, the entire length of new pipe is hydrostatically tested to ensure the integrity of the system. This is done by filling the pipe with water, pressurizing the system above its maximum operating conditions and holding the pressure for a specified time. The pipe is drained, cleaned and dried before put into service.
- Clean-up and restore ROW - The final step is to repair the surface over the trench. If necessary, fences or sod may also be replaced.
- Directional bore - At some busy intersections, most water crossings and under major roads, instead of trenching, crews will install pipe by boring horizontally underneath the road, stream or canal. The boring machine drills a hole from one side of the road or stream. Pipe is strung on the other side and then pulled back through hole.
Pipeline safety
We take safety seriously. Since its founding in 1929, our company and its affiliates have engaged in every phase of natural gas service, from production and gathering to transportation and distribution. During that time, while delivering the clean and efficient natural gas our customers rely on daily for their comfort and livelihood, we have earned an enviable record for safety and reliability.
Visit our safety section on this site for more details.
Project overview
Need for the project: These improvements are necessary for Enbridge Gas Utah to keep pace with growing customer demand for natural gas, maintain overall system integrity and continue providing safe and reliable service.
Location: This section of natural gas pipeline is located in downtown Salt Lake City. Work will take place at all intersections of 200 South from 400 West to 200 South. To minimize the inconvenience to businesses and residences, Enbridge Gas is working in conjunction with Salt Lake City's 200 South corridor project.
Construction schedule: We are committed to completing this work as quickly and with as little inconvenience to local businesses and residents as possible. Crews are scheduled to start in Spring 2023. To expedite construction, multiple crews may be working simultaneously at various locations and may perform nighttime and weekend work. No interruption to residents' natural gas service is anticipated during this project. Work will be completed in two phases. Phase I will start in Spring 2022 and end in Winter 2022. Phase II will start in Spring 2023 and will continue into 2024.
To provide room for crews and equipment, some temporary lane restrictions, especially at intersections, will be necessary. Please drive carefully and obey all signs and flaggers. To avoid congestion in construction zones, motorists are advised to use alternate routes when possible and to allow plenty of travel time to get where they're going. At all times, our crews will make every effort to maintain access to businesses and driveways in construction zones.
We appreciate your patience.
Construction process
Enbridge Gas Utah is committed to completing this project safely and on schedule while minimizing as much as possible any inconvenience to local businesses and residents. To accomplish this, some work may be performed at night and on weekends. This will reduce impacts on morning and evening commutes. We will adhere to all county noise-reduction ordinances.
Construction zones
For pipe buried beneath streets or highways, construction may require intermittent closures of one or more lanes of traffic. Driveways also may be occasionally blocked by excavation work, otherwise they will be plated to maintain access during business hours and at night and on weekends.
Before construction starts in front of any home or business, a representative will contact the owner or resident to discuss options for maintaining driveway access. Signs notifying the public that businesses remain open during construction are available.
To finish construction on schedule and as quickly as possible, the project is divided into sections, or "spreads." This allows multiple crews to work simultaneously at different locations. Work zones can range from a single intersection to several blocks long. At any one location the amount of time to cut pavement, install new pipe and replace asphalt can range from several days to several weeks.
The public can do its part to ensure construction proceeds safely and on time by finding alternative routes, driving carefully in construction zones and keeping children away from construction sites.
Enbridge Gas works closely with city and state transportation officials to ensure safety and minimize inconvenience to drivers and pedestrians. However, for public safety it may be necessary to temporarily close streets and sidewalks or restrict vehicle and pedestrian traffic. As mentioned, driveways may occasionally be blocked by excavation work. We will make every effort to keep these inconveniences as brief as possible. Your patience is appreciated.
If you have questions or concerns, do not hesitate to contact us.
Steps during construction
Following are brief descriptions of the steps involved in pipeline removal and construction:
- Locate buried utilities - The area below city streets can be a maze of underground utilities. To avoid damaging these facilities, a procedure known as potholing is used prior to trenching to identify the exact vertical and horizontal location of existing infrastructure, including the pipeline to be replaced.
- Move existing utilities - Before trenching (see next step), all water and natural gas service lines that cross the existing pipe will be moved to a lower depth. This will minimize the risk of interrupting water- or gas-service to individual homes or businesses once actual construction begins.
- Dig trench - After the pipe has been located and purged of gas and service lines in the trench zone moved, the pavement above the existing pipe is cut and removed. Then equipment is brought in to dig the trench. The depth of the natural gas pipeline trench will be determined by the location of the existing pipe and other utilities. As the trench is dug, the soil is loaded into trucks and hauled away for disposal in a designated landfill.
- Remove old pipe - Sections of pipe to be removed are cut into lengths, lifted from the trench, loaded onto trucks and hauled away for proper disposal.
- Deliver and "string" new pipe - New pipe is manufactured and inspected to ensure it meets industry and federal safety standards. Pipe sections are then delivered by truck to the construction site where they are placed end-to-end (or "strung") on skids adjacent to the trench. If necessary, a hydraulic machine bends pipe sections to fit around obstacles or conform to the direction of the trench.
- Weld new pipe together and coat - Welding crews join the sections of pipe together into a continuous length. Each welded joint is visually inspected, x-rayed and then coated for protection.
- Lower pipe into trench - Using one or more tractors, crews lift and then carefully lower the welded sections of pipe into the trench. Final welds are made to "tie-in" any unconnected sections.
- Backfill trench - Under streets, in place of the removed soil, a mixture known as "flowable fill" is used to backfill the trench. In other areas, the original soil is replaced.
- Pressure test new pipe - After it's buried and before it's put into service, the entire length of new pipe is hydrostatically tested to ensure the integrity of the system. This is done by filling the pipe with water, pressurizing the system above its maximum operating conditions and holding the pressure for a specified time. The pipe is drained, cleaned and dried before put into service.
- Clean-up and restore ROW - The final step is to repair the surface over the trench. If necessary, fences or sod may also be replaced.
- Directional bore - At some busy intersections, most water crossings and under major roads, instead of trenching, crews will install pipe by boring horizontally underneath the road, stream or canal. The boring machine drills a hole from one side of the road or stream. Pipe is strung on the other side and then pulled back through hole.
Pipeline safety
We take safety seriously. Since its founding in 1929, our company and its affiliates have engaged in every phase of natural gas service, from production and gathering to transportation and distribution. During that time, while delivering the clean and efficient natural gas our customers rely on daily for their comfort and livelihood, we have earned an enviable record for safety and reliability.
Visit our safety section on this site for more details.